Menu Commercial Water Resources Heavy Civil

Chattanooga Wet Weather CSS

This highly complex project for the City of Chattanooga involves the construction of three 10 million gallon, pre-stressed, concrete storage tanks, one cast-in-place 40 MGD pump station including four 10 MGD submersible pumps, and one cast-in-place diversion structure incorporating an existing 84” gravity sewer, two carbon absorption odor control units, one electrical building including switchgear, VFDs, 600 KW standby generator, automatic transfer switch, restrooms, and HVAC units. The project also includes construction of a cast-in-place valve and flow meter vaults and two retaining walls. Installation of buried and above ground piping ranging in size from 8” to 54” diameter was also required on the site, including 680 LF of 36” diameter force main pipe, as well as micropiles for construction. Replacement of electrical gear at the existing Influent Relief Pump Station was also required. Modifications will also be made to the existing West Bank Outfall, including demolition and a new metal weir box.

Johnson Creek Pump Station

Reeves Young provided construction services for this new, 10 MGD sewage pump station which also required an expedited schedule due to a consent order from the Georgia Natural Resources Environmental Protection Division. The project included placement of approximately 5,000 CY of cast-in-place concrete, rock excavation, and a 48” gravity sewer. Installed equipment included submersible pumps, slide gates, odor control system, and a 5-ton bridge crane.

Lithonia Pump Station No. 1

This project was a fast-track design-build for a 10 MGD pump station. It included a 30-foot excavation in solid rock; 5,000 CY of cast-in-place concrete, 30,000 CY of rock excavation, and 3,000 LF of pipe. The project required work performed in multiple shifts, 24 hours a day, seven days a week. Equipment included submersible pumps, chopper pumps, slide gates, an odor control system, and a magnesium hydraulic feed system. A temporary bypass of the existing facility also was required for the duration of the project.