Project Description

Client: City of Fayetteville
Location: Fayetteville, GA

Scope consists of upgrading an existing 5.0 MGD wastewater facility, which includes constructing new splitter boxes, clarifiers, RAW/WAS pump station; converting existing SBR to A2/O process; retrofitting existing tertiary filters; replacing digester process equipment, existing belt press, chemical feed equipment; and removing CAS process from service. Preconstruction Phase services includes value-engineering and GMP development/negotiation. Construction Phase services includes construction document management, project schedule, budget reporting, design compliance review, start-up and commissioning, operator training, and project closeout.